Hi Everybody

Update of Progress.
Good morning Roy,

I trust you are well.

Apologies for the delay in responding but I have been waiting for a reply from the Staffordshire County Council street lighting contractor E.on with regards the programming of the signage works for the 7.5t weight limit.

They are currently expecting delivery of the steel columns w/c 14.02.2022 at which point they will programme in the works. If the materials arrive on time then they anticipate being on site in approximately 6 weeks’ time – end of March/early April.

I contact them again on, or around, the 14th Feb to ensure that the posts have been delivered and to see if there is a possibility to programme these works any earlier than the 6 weeks.

Regards,

John